Hello there, I'm using Revit Structure 09. I am wondering if anyone knows why when I paint both sides of a wall, sometimes both sides and sometime only one side get taken off in a material takeoff. I would put the material in the wall family, but I need a different material based on the height of the wall. The only way to get it to take it off of both sides, is to rebuild the wall and then paint it again. I'm confused. Like I said too, sometimes it does work the first time, just don't know why. Any ideas. Thanks.
|
This user is offline |
|
|
|
site moderator|||
Joined: Tue, May 22, 2007
5921 Posts
|
Hi, can you put some images about this? to see what do you trying to do?
-----------------------------------
I Hope and I Wish to LEARN more, and more, and more.... REVIT |
This user is offline |
|
|
site moderator|||
Joined: Tue, May 16, 2006
13079 Posts
|
As far as I know, the paint bucket tool does not schedule.
|
This user is offline |
|
|
active
Joined: Thu, Nov 10, 2005
390 Posts
|
Paint bucket should schedual if you do a material schedual. The bigger issue that I see is that neither the paint bucket nor verticly changing walls (ie red brick from 0-3', white brick 3'-6', green brick 6'-9') will export to schedualing software such as QTO.
|
This user is offline |
|
|
site moderator|||
Joined: Tue, May 16, 2006
13079 Posts
|
I stand corrected .... paint bucket will schedule some of the time. It doesn't seem to schedule on a stacked wall where I split the face however. I should not say schedule ... because I'm not looking at that, I'm looking at the takeoff.
Edited on: Mon, Aug 11, 2008 at 11:22:46 AM
|
This user is offline |
|
|
active
Joined: Tue, May 29, 2007
48 Posts
|
You are correct WWHub. I figured out that it will not take off the painted ends, tops, or ledges of a split wall. Even on some normal walls though, out of nowhere, it decides to not takeoff the normal sides of some walls, at random. It is just on the current project I am working on. I visually shows that it is painted, but will not show up in the schedule? I think I have a work around though. I just built a wall sweep to cover the parts of the walls that I want, and I can rely on that a little more. Thanks
|
This user is offline |
|
|
|
Similar Threads |
Material Takeoff walls/floors |
Revit Building >> Technical Support
|
Mon, Apr 30, 2012 at 6:57:03 AM
|
9
|
Material Takeoff for Demoed Walls |
Revit Building >> Technical Support
|
Thu, Apr 5, 2012 at 1:36:50 PM
|
2
|
Material takeoff: Walls appearing in wrong takeoff |
General Discussion >> Revit Project Management
|
Wed, Sep 7, 2016 at 3:45:24 PM
|
1
|
Material Takeoff |
Community >> Newbies
|
Mon, Apr 27, 2015 at 7:32:15 AM
|
5
|
Sheathing Material Takeoff |
Revit Building >> Technical Support
|
Mon, Apr 25, 2011 at 7:01:06 AM
|
1
|
|
|
Site Stats
Members: | 2057190 | Objects: | 23074 | Forum Posts: | 152250 | Job Listings: | 3 |
|